Halse Farm (8.2 MW solar farm)

Halse Farm is an 8.2 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2013; the record was last updated on 14 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.2 MWsolar farm
operationalstatus in REPD
14 June 2013record last updated
Somersetcouncil area

Planning timeline

DateStage
15 June 2012Application submitted
6 September 2012Planning permission granted
28 March 2013Operational

Project details

Technology
solar farm
Capacity
8.2 MW
Status (REPD)
operational
Record last updated
14 June 2013
Operator or applicant
AEE Renewables
Planning authority
Somerset
Planning application reference
06/12/0034
Address (REPD)
Bishop's Lydeard, TA4 3LZ
Council area (by location)
Somerset
Time to decision
12 weeks
REPD reference
1349

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pixford Fruit Farmsolar farm5refused on appeal1.9
The Village Of Halsesolar farm25approved, not built2.1
Montys Farmsolar farm5operational3.9
Fideoak Millsbattery storage30operational5.4
Hele Manor Farm, Bradford On Tonebattery storage20approved, not built5.5
Taunton Substationbattery storage49.9permission expired5.5
RITHERDENS FARM solar parksolar farm9.5refused5.8
Lower Marsh Farmsolar farm5operational6.9
Tonedale Farmsolar farm5operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0517, -3.2126).