Energy Projects Near You

Ham Farm, Creech St Michael (20 MW solar farm)

Ham Farm, Creech St Michael is a 20 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 June 2024, not yet built; the record was last updated on 22 July 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
22 July 2024record last updated
Somersetcouncil area

Planning timeline

DateStage
17 November 2022Application submitted
28 June 2024Planning permission granted
28 June 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
22 July 2024
Operator or applicant
Novus Renewable Services Limited
Planning authority
Somerset
Planning application reference
14/22/0051
Site area
10.8 ha
Address (REPD)
Ham Farm, Ham, Creech St Michael.
Council area (by location)
Somerset
Time to decision
84 weeks
Name in REPD
Ham Farm, Creech St Michael - Solar Array
REPD reference
10495

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bull Street, Creech St Michael Solar Farmsolar farm34application submitted1.0
North Newton Solar Farmsolar farm30application submitted5.8
Impens Farm Solar Farm & Battery Storagesolar farm49.9approved, not built6.7
Lower Marsh Farmsolar farm5operational8.5
Langport Farmsolar farm5application withdrawn9.2
Taunton Substationbattery storage49.9permission expired9.4
Fideoak Millsbattery storage30operational9.4
RITHERDENS FARM solar parksolar farm9.5refused9.5
Bushfurlong Solar Farmsolar farm5application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0203, -3.0205).