Energy Projects Near You

Culmhead Solar Farm (7.5 MW)

Culmhead Solar Farm is a 7.5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 January 2014; the record was last updated on 3 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWsolar farm
operationalstatus in REPD
3 April 2014record last updated
Somersetcouncil area

Planning timeline

DateStage
11 September 2012Application submitted
19 October 2012Planning permission granted
26 January 2014Operational

Project details

Technology
solar farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
3 April 2014
Operator or applicant
Anesco
Planning authority
Somerset
Planning application reference
10/12/0024
Site area
21.4 ha
Address (REPD)
Former Culmhead Airfield, Culmhead, Churchstanton, Taunton,
Council area (by location)
Somerset
Time to decision
5 weeks
REPD reference
1603

Earlier applications for this site

ApplicationMWSubmittedOutcome
Culmhead Solar Farm 10/12/0009517 April 2012withdrawn 19 June 2012

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunkeswell Airfieldbattery storage6.5approved, not built9.8
RITHERDENS FARM solar parksolar farm9.5refused9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9261, -3.128).