Hornsea 2 - Optimus and Breesea offshore wind farm

Hornsea 2 - Optimus and Breesea is a 1,320 MW offshore wind farm with 165 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 August 2022; the record was last updated on 1 September 2022. Its REPD grid reference is 100 km from the nearest postcode on land (HU12 0SX, East Riding of Yorkshire). As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010053).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,320 MWoffshore wind farm
operationalstatus in REPD
1 September 2022record last updated
100 km from land (East Riding of Yorkshire)REPD location

Consent timeline

DateStage
30 January 2015Application submitted
16 August 2016Development consent granted (Secretary of State)
1 September 2019Construction started
31 August 2022Operational

Project details

Technology
offshore wind farm
Capacity
1,320 MW
Turbines
165
Turbine capacity
8 MW
Status (REPD)
operational
Record last updated
1 September 2022
Operator or applicant
Orsted (formerly Dong Energy)
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010053
Nearest postcode on land
HU12 0SX (East Riding of Yorkshire), 99.7 km from the REPD grid reference
Time to decision
81 weeks
Contracts for Difference
AR2
REPD reference
2502

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010053). All Energy Secretary decisions on solar and wind farms.

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.96, 1.54).