Humble Hill Wind Farm (78.5 MW)

Humble Hill Wind Farm is a 78.5 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 2 May 2002; the record was last updated on 2 November 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

78.5 MWwind farm
refused on appealstatus in REPD
2 November 2011record last updated
Northumberlandcouncil area

Planning timeline

DateStage
13 April 1993Application submitted
2 May 2002Refused by the planning authority
2 May 2002Appeal refused

Project details

Technology
wind farm
Capacity
78.5 MW
Status (REPD)
refused on appeal
Record last updated
2 November 2011
Operator or applicant
Ecogen
Planning authority
Northumberland
Planning application reference
not recorded
Address (REPD)
Humble Hill Kielder Forest Hexham Northumberland
Council area (by location)
Northumberland
Time to decision
472 weeks
REPD reference
3508

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1221, -2.5503).