Energy Projects Near You

Land Off Folly Lane (5 MW solar farm)

Land Off Folly Lane is a 5 MW solar farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 March 2016; the record was last updated on 28 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
28 July 2016record last updated
East Lindseycouncil area

Planning timeline

DateStage
18 June 2015Application submitted
17 September 2015Planning permission granted
5 January 2016Construction started
7 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
28 July 2016
Operator or applicant
Solar Century/ Bluefield Solar
Planning authority
East Lindsey
Planning application reference
S/203/01106/15
Site area
8.3 ha
Address (REPD)
Land Off, Folly Lane, Stickney, Boston, Lincolnshire
Council area (by location)
East Lindsey
Time to decision
13 weeks
REPD reference
5483

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mallows Lane Solar Farm & Battery Storagesolar farm10approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1061, -0.0199).