Energy Projects Near You

Mallows Lane Solar Farm & Battery Storage (10 MW)

Mallows Lane Solar Farm & Battery Storage is a 10 MW solar farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 December 2022, not yet built; the record was last updated on 23 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
23 February 2026record last updated
East Lindseycouncil area

Planning timeline

DateStage
21 July 2022Application submitted
19 December 2022Planning permission granted
19 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
23 February 2026
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
East Lindsey
Planning application reference
S/152/01297/22
Site area
20.4 ha
Address (REPD)
W/O Mallows Lane & N/O Pymoor Lane, Sibsey, Boston
Council area (by location)
East Lindsey
Time to decision
22 weeks
Contracts for Difference
AR7a
Name in REPD
Mallows Lane - Solar Farm & Battery Storage
REPD reference
11654

The scheme also includes 5.3 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Leverton Ingssolar farm12operational4.3
Canopus Farmsolar farm5operational6.1
Land Off Folly Lanesolar farm5operational7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0456, 0.0148).