Canopus Farm (5 MW solar farm)

Canopus Farm is a 5 MW solar farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 December 2015; the record was last updated on 14 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
14 August 2017record last updated
East Lindseycouncil area

Planning timeline

DateStage
5 January 2015Application submitted
26 March 2015Planning permission granted
26 August 2015Construction started
10 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
14 August 2017
Operator or applicant
Countryside Renewables
Planning authority
East Lindsey
Planning application reference
S/054/02433/14
Site area
12.1 ha
Address (REPD)
Land Associates With Canopus F, Frith Bank, Boston, Lincolnshire
Council area (by location)
East Lindsey
Time to decision
11 weeks
REPD reference
4951

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Friths Farmsolar farm28permission expired5.5
Mallows Lane Solar Farm & Battery Storagesolar farm10approved, not built6.1
Boston Landfill, Wybertonsolar farm9.7under construction7.1
Leverton Ingssolar farm12operational8.0
Nowhere Farmsolar farm8.1operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0099, -0.055).