Friths Farm (28 MW solar farm)

Friths Farm is a 28 MW solar farm project in Boston, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 9 October 2017; the record was last updated on 24 November 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWsolar farm
permission expiredstatus in REPD
24 November 2017record last updated
Bostoncouncil area

Planning timeline

DateStage
4 August 2014Application submitted
9 October 2014Planning permission granted
9 October 2017Permission expired

Project details

Technology
solar farm
Capacity
28 MW
Status (REPD)
permission expired
Record last updated
24 November 2017
Operator or applicant
Friths Solar Limited
Planning authority
Boston
Planning application reference
B/14/0287
Site area
52.6 ha
Address (REPD)
Land at Friths Farm, Fen Road, Frampton West, Boston, Lincolnshire, PE201SA
Council area (by location)
Boston
Time to decision
9 weeks
REPD reference
2267

Who decides

ApplicationsBostonUK
Decided applications (solar, wind, battery)1910,236
Refused1 (5%)19%
Solar refused1 of 1412%
Onshore wind refused0 of 145%
Battery storage refused0 of 416%
Median time from submission to decision14.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nowhere Farmsolar farm8.1operational4.6
Boston Landfill, Wybertonsolar farm9.7under construction4.7
Canopus Farmsolar farm5operational5.5
Bicker Drovebattery storage100approved, not built9.3
Heckington Fen Solar Parksolar farm500approved, not built9.5
Bicker Fen Bess, Vicarage Drovebattery storage400approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9607, -0.0685).