Energy Projects Near You

Limekiln Wind Farm (79.8 MW)

Limekiln Wind Farm is a 79.8 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2025; the record was last updated on 11 April 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

79.8 MWwind farm
operationalstatus in REPD
11 April 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
15 June 2016Application submitted
7 April 2017Appeal lodged
21 June 2019Section 36 consent granted (Scottish Ministers)
21 June 2019Appeal allowed
1 April 2025Operational

Project details

Technology
wind farm
Capacity
79.8 MW
Status (REPD)
operational
Record last updated
11 April 2025
Operator or applicant
Boralex/Infinergy
Planning authority
Scottish Government (S36)
Planning application reference
EC00005269
Appeal reference
WIN-270-8
Turbines
19
Turbine height
150 m
Address (REPD)
Limekilns Estate, Reay, Thurso
Council area (by location)
Highland
Time to decision
157 weeks
Contracts for Difference
AR5
REPD reference
6005

Earlier applications for this site

ApplicationMWSubmittedOutcome
Limekiln Wind Farm EC000031707214 December 2012refused 23 July 2015

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Limekiln Wind Farm (Extension)wind farm21operational1.6
Limekiln Wind Farm (Extension) Batterybattery storage5operational1.6
South Shebsterwind farm10refused3.4
Broubster Forestwind farm116application withdrawn3.4
Titan Battery Storagebattery storage500application submitted3.5
Limekiln, Borlum Housebattery storage70application submitted3.9
Dounreay, Thursobattery storage34under construction4.4
Dounreay Windfarmwind farm17.5refused on appeal5.0
Hillcrest Cottage, Shebsterbattery storage19.9approved, not built5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5285, -3.742).