Energy Projects Near You

Lochcarnan Community Windfarm (6.9 MW)

Lochcarnan Community Windfarm is a 6.9 MW wind farm project in Na h-Eileanan Siar, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 February 2013; the record was last updated on 16 July 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
operationalstatus in REPD
16 July 2020record last updated
Na h-Eileanan Siarcouncil area

Planning timeline

DateStage
4 December 2008Application submitted
21 December 2011Planning permission granted
21 March 2012Construction started
18 February 2013Operational

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
operational
Record last updated
16 July 2020
Operator or applicant
Storas Uibhist
Planning authority
Na h-Eileanan Siar
Planning application reference
08/00561/FUL
Turbines
3
Address (REPD)
Lochcarnan, Isle of South Uist. HS8 5
Council area (by location)
Na h-Eileanan Siar
Time to decision
159 weeks
REPD reference
3670

Who decides

ApplicationsNa h-Eileanan SiarUK
Decided applications (solar, wind, battery)1510,236
Refused2 (13%)19%
Onshore wind refused2 of 1445%
Battery storage refused0 of 116%
Median time from submission to decision79.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2337, -7.3479).