Renewable energy projects in Na h-Eileanan Siar
19 solar, wind or battery projects of 150 kW or more are located in Na h-Eileanan Siar (REPD, July 2026 extract): 1 pending, 7 approved but not running, 5 operational and 3 refused. The council refused 2 of 15 decided applications (13%; UK 19%), with a median 79 weeks from submission to decision.
19projects in the council area
1awaiting a decision
7approved, not running
13%of decisions refused
How Na h-Eileanan Siar decides
| Applications | Na h-Eileanan Siar | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 2 (13%) | 19% |
| Onshore wind refused | 2 of 14 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 79.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Projects in Na h-Eileanan Siar
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Lewis Wind Farm (Barvas Moor)wind farm | wind farm | 652 | refusedupdated Apr 2008 | Nov 2004 | refused Apr 2008 | Apr 2008 |
| Stornoway Wind Farm (second resubmission)wind farm | wind farm | 196 | approved, not built may be out of dateupdated Mar 2024 | May 2019 | granted Jan 2022 | Mar 2024 |
| Uisenis Wind Farmwind farm | wind farm | 165 | approved, not builtupdated Oct 2025 | Aug 2023 | granted Sep 2025 | Oct 2025 |
| Pairc Windfarmwind farm | wind farm | 94 | application withdrawnupdated Aug 2012 | — | — | Aug 2012 |
| Sandwick East Community Wind Farmwind farm | wind farm | 49.9 | application submitted may be out of dateupdated Jun 2019 | Apr 2019 | — | Jun 2019 |
| Druim Leathann Windfarmwind farm | wind farm | 48.3 | approved, not built may be out of dateupdated Oct 2025 | Jun 2018 | granted Jun 2022 | Oct 2025 |
| Battery Energy Storage Parkbattery storage | battery storage | 25 | approved, not builtupdated Jan 2025 | Apr 2024 | granted Dec 2024 | Jan 2025 |
| Point Wind / Beinn Ghrideag Farmwind farm | wind farm | 9 | operationalupdated Jan 2017 | Aug 2008 | granted Apr 2012 | Jan 2017 |
| Lochcarnan Community Windfarmwind farm | wind farm | 6.9 | operationalupdated Jul 2020 | Dec 2008 | granted Dec 2011 | Jul 2020 |
| Lochdar Hill Wind Farmwind farm | wind farm | 6.9 | application withdrawnupdated Sep 2020 | Dec 2015 | — | Sep 2020 |
| Sandwick North St Community wind turbinewind turbine | wind turbine | 5 | approved, not built may be out of dateupdated Sep 2020 | Jan 2017 | granted Nov 2019 | Sep 2020 |
| Beinn Thulabaigh Wind Turbinewind turbine | wind turbine | 5 | approved, not built may be out of dateupdated Sep 2020 | May 2019 | granted May 2020 | Sep 2020 |
| Arnish Moorwind farm | wind farm | 3.9 | operationalupdated Feb 2010 | Jun 2001 | granted Sep 2001 | Feb 2010 |
| Loch Sminig Wind Projectwind farm | wind farm | 2.7 | operationalupdated Jun 2016 | Aug 2008 | granted May 2009 | Jun 2016 |
| North Harris Community Trustwind farm | wind farm | 2.5 | abandonedupdated Jun 2011 | Jul 2006 | granted Feb 2008 | Jun 2011 |
| Kirkibost Wind Farmwind farm | wind farm | 1.8 | refusedupdated Jul 2013 | Aug 2011 | refused Jan 2013 | Jul 2013 |
| Locheport wind turbineswind farm | wind farm | 1.8 | refusedupdated Nov 2014 | Apr 2013 | refused Oct 2014 | Nov 2014 |
| Monan Hill Wind Turbineswind farm | wind farm | 1.5 | operationalupdated Mar 2015 | May 2006 | granted Feb 2008 | Mar 2015 |
Smaller schemes under 1 MW, mostly rooftop solar (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Wind Turbines at Monan Wind Farmwind farm | wind farm | — | approved, not builtupdated Aug 2024 | Apr 2024 | granted Mar 2025 | Aug 2024 |
Postcode districts in Na h-Eileanan Siar
| District | Projects within 10 km | Pending | Approved | Operational |
|---|---|---|---|---|
| HS1 | 7 | 0 | 3 | 3 |
| HS2 | 7 | 0 | 3 | 3 |
| HS3 | 3 | 0 | 1 | 1 |
| HS4 | 0 | 0 | 0 | 0 |
| HS5 | 0 | 0 | 0 | 0 |
| HS6 | 1 | 0 | 0 | 0 |
| HS7 | 1 | 0 | 0 | 0 |
| HS8 | 1 | 0 | 0 | 1 |
| HS9 | 0 | 0 | 0 | 0 |
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Na h-Eileanan Siar by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.