Energy Projects Near You

Solar, wind and battery projects near Stornoway (HS1)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HS1 (Na h-Eileanan Siar): 3 approved but not yet running, 3 operational. The largest live scheme is Stornoway Wind Farm (second resubmission) (196 MW wind farm, approved on 5 January 2022, not yet built; REPD status may be out of date), 0.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
3approved, not running
3operational

Projects within 10 km of HS1

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lewis Wind Farm (Barvas Moor)wind farmwind farm652refusedupdated Apr 2008Nov 2004refused Apr 2008Apr 2008Na h-Eileanan Siar0.8
Stornoway Wind Farm (second resubmission)wind farmwind farm196approved, not built may be out of dateupdated Mar 2024May 2019granted Jan 2022Mar 2024Na h-Eileanan Siar0.8
Battery Energy Storage Parkbattery storagebattery storage25approved, not builtupdated Jan 2025Apr 2024granted Dec 2024Jan 2025Na h-Eileanan Siar1.0
Arnish Moorwind farmwind farm3.9operationalupdated Feb 2010Jun 2001granted Sep 2001Feb 2010Na h-Eileanan Siar5.2
Point Wind / Beinn Ghrideag Farmwind farmwind farm9operationalupdated Jan 2017Aug 2008granted Apr 2012Jan 2017Na h-Eileanan Siar5.8
Beinn Thulabaigh Wind Turbinewind turbinewind turbine5approved, not built may be out of dateupdated Sep 2020May 2019granted May 2020Sep 2020Na h-Eileanan Siar5.9
Pentland Road Wind Farmwind farmwind farm13.8operationalupdated Jun 2013Sep 2002granted Sep 2004Jun 2013—9.1

Distance from the average position of the HS1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm50131196
Wind turbine101005
Battery storage1010025

MW in pipeline: pending, approved and under-construction capacity.

How Na h-Eileanan Siar decides solar, wind and battery applications

ApplicationsNa h-Eileanan SiarUK
Decided applications (solar, wind, battery)1510,236
Refused2 (13%)19%
Onshore wind refused2 of 1445%
Battery storage refused0 of 116%
Median time from submission to decision79.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Na h-Eileanan Siar

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HS1, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.