Pentland Road Wind Farm (13.8 MW)

Pentland Road Wind Farm is a 13.8 MW wind farm project in Western Isles, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2013; the record was last updated on 3 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
operationalstatus in REPD
3 June 2013record last updated
Scotlandcouncil area

Planning timeline

DateStage
30 September 2002Application submitted
6 September 2004Planning permission granted
1 March 2012Construction started
28 March 2013Operational

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
operational
Record last updated
3 June 2013
Operator or applicant
Arnish Electric Ltd / Farm Energy Ltd
Planning authority
Na h-Eileanan Siar
Planning application reference
02/00404/PPD
Turbines
6
Address (REPD)
Pentland Road, Isle of Lewis
Council area (by location)
not known
Time to decision
101 weeks
REPD reference
4063

Who decides

ApplicationsNa h-Eileanan SiarUK
Decided applications (solar, wind, battery)1510,236
Refused2 (13%)19%
Onshore wind refused2 of 1445%
Battery storage refused0 of 116%
Median time from submission to decision79.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Point Wind / Beinn Ghrideag Farmwind farm9operational5.8
Beinn Thulabaigh Wind Turbinewind turbine5approved, not built6.1
Lewis Wind Farm (Barvas Moor)wind farm652refused8.6
Stornoway Wind Farm (second resubmission)wind farm196approved, not built8.6
Battery Energy Storage Parkbattery storage25approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.2572, -6.5108).