Energy Projects Near You

Solar, wind and battery projects near Balivanich (HS7)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of HS7 (Na h-Eileanan Siar): none of them is pending, approved or operational. The largest scheme is Lochdar Hill Wind Farm (6.9 MW wind farm, application withdrawn on 26 June 2020), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of HS7

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lochdar Hill Wind Farmwind farmwind farm6.9application withdrawnupdated Sep 2020Dec 2015—Sep 2020Na h-Eileanan Siar10.0

Distance from the average position of the HS7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm100000

MW in pipeline: pending, approved and under-construction capacity.

How Na h-Eileanan Siar decides solar, wind and battery applications

ApplicationsNa h-Eileanan SiarUK
Decided applications (solar, wind, battery)1510,236
Refused2 (13%)19%
Onshore wind refused2 of 1445%
Battery storage refused0 of 116%
Median time from submission to decision79.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Na h-Eileanan Siar

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.