Energy Projects Near You

Solar, wind and battery projects near Glen Dale (IV55)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV55 (Highland): 2 operational. The largest scheme is Ben Aketil (23 MW wind farm, operational since 1 September 2007), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
0approved, not running
2operational

Projects within 10 km of IV55

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ben Aketilwind farmwind farm23operationalupdated May 2009Aug 2002granted Sep 2005May 2009Highland9.5
Ben Aketil Extensionwind farmwind farm4.6operationalupdated Feb 2012Apr 2009granted Feb 2010Feb 2012Highland9.5

Distance from the average position of the IV55 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm200200

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.