Energy Projects Near You

Solar, wind and battery projects near Struan (IV56)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV56 (Highland): 4 are waiting for a planning decision, 1 approved but not yet running, 2 operational. The largest live scheme is Glen Ullinish II Wind Farm (310 MW wind farm, application submitted on 31 July 2023, no decision recorded; REPD status may be out of date), 1.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
4awaiting a decision
1approved, not running
2operational

Projects within 10 km of IV56

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Glen Ullinish II Wind Farmwind farmwind farm310application submitted may be out of dateupdated Apr 2022Jul 2023—Apr 2022Highland1.7
Glen Ullinish II Wind Farmbattery storagebattery storage120application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023Highland1.7
Beinn Mheadhonach Hill Wind Farmwind farmwind farm21application submitted may be out of dateupdated Aug 2025Jan 2024—Aug 2025Highland2.3
Glen Ullinish Wind Farmwind farmwind farm49.9approved, not builtupdated Feb 2026Oct 2014granted Mar 2015Feb 2026Highland3.4
An Cleireach, Balmeanach Wind Farm & Battery Storagewind farmwind farm45refusedupdated Jul 2026Aug 2023refused Feb 2026Jul 2026Highland4.4
Beinn Mheadhonachwind farmwind farm4permission expiredupdated Feb 2024Jul 2018granted Aug 2019Feb 2024Highland5.8
Ben Aketilwind farmwind farm23operationalupdated May 2009Aug 2002granted Sep 2005May 2009Highland7.3
Ben Aketil Extensionwind farmwind farm4.6operationalupdated Feb 2012Apr 2009granted Feb 2010Feb 2012Highland7.3
Ben Scawind farmwind farm40.8application submitted may be out of dateupdated Aug 2025Apr 2024—Aug 2025Highland8.7

Distance from the average position of the IV56 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm83121422
Battery storage11000120

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IV56, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.