Glen Ullinish Wind Farm (49.9 MW)

Glen Ullinish Wind Farm is a 49.9 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 March 2015, not yet built; the record was last updated on 23 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWwind farm
approved, not builtstatus in REPD
23 February 2026record last updated
Highlandcouncil area

Planning timeline

DateStage
28 October 2014Application submitted
24 March 2015Planning permission granted
21 December 2026Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
23 February 2026
Operator or applicant
Muirhall Energy (previously Kilmac Energy)
Planning authority
Highland
Planning application reference
14/03964/FUL
Turbines
11
Turbine height
150 m
Address (REPD)
Land 1800M SE Of Balmenach, , Glen Ullinish, Struan, Isle Of Skye, Highlands, IV56 8F
Council area (by location)
Highland
Time to decision
21 weeks
Contracts for Difference
AR7a
REPD reference
2859

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
An Cleireach, Balmeanach Wind Farm & Battery Storagewind farm45refused3.4
Glen Ullinish II Wind Farmwind farm310application submitted4.5
Beinn Mheadhonach Hill Wind Farmwind farm21application submitted4.6
Ben Aketilwind farm23operational4.7
Ben Scawind farm40.8application submitted5.6
Edinbane Wind Farmwind farm41.4operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3948, -6.4149).