Energy Projects Near You

Glen Ullinish II Wind Farm (310 MW)

Glen Ullinish II Wind Farm is a 310 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 31 July 2023, no decision recorded; the record was last updated on 12 April 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

310 MWwind farm
application submittedmay be out of datestatus in REPD
12 April 2022record last updated
Highlandcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
31 July 2023Application submitted

Project details

Technology
wind farm
Capacity
310 MW
Status (REPD)
application submitted
Record last updated
12 April 2022
Operator or applicant
Muirhall Energy Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004829
Turbines
47
Turbine height
200 m
Address (REPD)
Glen Ullinish, Isle of Skye
Council area (by location)
Highland
Name in REPD
Glen Ullinish II - Wind Farm
REPD reference
11000

The scheme also includes 120 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Beinn Mheadhonach Hill Wind Farmwind farm21application submitted0.8
Glen Ullinish Wind Farmwind farm49.9approved, not built4.5
An Cleireach, Balmeanach Wind Farm & Battery Storagewind farm45refused6.1
Ben Aketilwind farm23operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3542, -6.411).