An Cleireach, Balmeanach Wind Farm & Battery Storage (45 MW)

An Cleireach, Balmeanach Wind Farm & Battery Storage is a 45 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 February 2026; the record was last updated on 13 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWwind farm
refusedstatus in REPD
13 July 2026record last updated
Highlandcouncil area

Planning timeline

DateStage
31 August 2023Application submitted
24 February 2026Refused by the planning authority

Project details

Technology
wind farm
Capacity
45 MW
Status (REPD)
refused
Record last updated
13 July 2026
Operator or applicant
Balmeanach Wind Farm Limited
Planning authority
Highland
Planning application reference
23/04194/FUL
Turbines
10
Turbine height
150 m
Address (REPD)
2400M NE Of An Cleireach 8 Balmeanach Struan
Council area (by location)
Highland
Time to decision
130 weeks
Name in REPD
An Cleireach, Balmeanach - Wind Farm & Battery Storage
REPD reference
12163

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glen Ullinish Wind Farmwind farm49.9approved, not built3.4
Ben Aketilwind farm23operational3.6
Ben Scawind farm40.8application submitted5.3
Glen Ullinish II Wind Farmwind farm310application submitted6.1
Beinn Mheadhonach Hill Wind Farmwind farm21application submitted6.6
Edinbane Wind Farmwind farm41.4operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3986, -6.4718).