Energy Projects Near You

Edinbane Wind Farm (41.4 MW)

Edinbane Wind Farm is a 41.4 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 June 2010; the record was last updated on 2 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41.4 MWwind farm
operationalstatus in REPD
2 December 2014record last updated
Highlandcouncil area

Planning timeline

DateStage
28 February 2002Application submitted
16 May 2007Planning permission granted
1 August 2008Construction started
21 June 2010Operational

Project details

Technology
wind farm
Capacity
41.4 MW
Status (REPD)
operational
Record last updated
2 December 2014
Operator or applicant
Vattenfall
Planning authority
Highland
Planning application reference
02/00089/FULSL
Turbines
18
Address (REPD)
Cruachan Brinn Mhicaskill, Edinbane, Portree, Highlands
Council area (by location)
Highland
Time to decision
272 weeks
REPD reference
4674

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ben Scawind farm40.8application submitted3.0
Ben Aketilwind farm23operational4.6
An Cleireach, Balmeanach Wind Farm & Battery Storagewind farm45refused8.2
Glen Ullinish Wind Farmwind farm49.9approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4691, -6.4322).