Marsh Lane, Gowhole (30 MW battery storage)

Marsh Lane, Gowhole is a 30 MW battery storage project in High Peak, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 January 2025, not yet built; the record was last updated on 17 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtstatus in REPD
17 June 2026record last updated
High Peakcouncil area

Planning timeline

DateStage
16 May 2023Application submitted
17 January 2025Planning permission granted
17 January 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
17 June 2026
Operator or applicant
Novus Renewable Services Limited
Planning authority
High Peak
Planning application reference
HPK/2023/0193
Address (REPD)
Marsh Lane, Gowhole, High Peak
Council area (by location)
High Peak
Time to decision
87 weeks
Name in REPD
Marsh Lane, Gowhole - Energy Storage System
REPD reference
13982

Who decides

ApplicationsHigh PeakUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused1 of 812%
Battery storage refused0 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dolly Lane, Buxworth Battery Storage Facility & Sub Stationbattery storage13approved, not built2.0
Torkington Road, Hazel Grovesolar farm30application submitted7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3511, -1.9848).