Solar, wind and battery projects near High Peak (SK22)
11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SK22 (High Peak): 1 is waiting for a planning decision, 10 approved but not yet running. The largest live scheme is Goyt Hall Farm, Goyt Valley Footpath (40 MW battery storage, approved on 23 August 2024, not yet built), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SK22
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Marsh Lane, Gowholebattery storage | battery storage | 30 | approved, not builtupdated Jun 2026 | May 2023 | granted Jan 2025 | Jun 2026 | High Peak | 2.4 |
| Dolly Lane, Buxworth Battery Storage Facility & Sub Stationbattery storage | battery storage | 13 | approved, not builtupdated Feb 2024 | Oct 2023 | granted Feb 2024 | Feb 2024 | High Peak | 3.9 |
| Torkington Road, Hazel Grovesolar farm | solar farm | 30 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | Stockport | 6.5 |
| Carpenter Plc, Dinting Lodge Industrial Estatesolar farm | solar farm | 1 | approved, not builtupdated May 2025 | Oct 2023 | granted Mar 2025 | May 2025 | High Peak | 8.7 |
| Goyt Hall Farm, Goyt Valley Footpathbattery storage | battery storage | 40 | approved, not builtupdated Sep 2024 | Dec 2023 | granted Aug 2024 | Sep 2024 | Stockport | 9.6 |
| Newby Road, Hazel Grovebattery storage | battery storage | 7.5 | approved, not built may be out of dateupdated May 2022 | Apr 2022 | granted Nov 2022 | May 2022 | Stockport | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| New Mills Leisure Centre, Hyde Bank Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | High Peak | 1.0 |
| Concept Life Sciences, Frith Knoll Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jul 2026 | Apr 2026 | granted Jun 2026 | Jul 2026 | High Peak | 7.6 |
| Frith Knoll Road, Walker Industrial Park, Units 1-5 Solar PV Modulesrooftop solar | rooftop solar | — | approved, not builtupdated Apr 2026 | Dec 2025 | granted Jan 2026 | Apr 2026 | High Peak | 7.6 |
| Glossop Caravans, Brookfieldrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Aug 2025 | Sep 2025 | High Peak | 9.0 |
| Sainsburys, London Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Stockport | 9.4 |
Distance from the average position of the SK22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 1 | 1 | 0 | 0 | 31 |
| Rooftop solar | 5 | 0 | 5 | 0 | 0 | 1.2 |
| Battery storage | 4 | 0 | 4 | 0 | 0 | 90.5 |
MW in pipeline: pending, approved and under-construction capacity.
How High Peak decides solar, wind and battery applications
| Applications | High Peak | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 1 (7%) | 19% |
| Solar refused | 1 of 8 | 12% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SK22, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.