Morecambe offshore wind farm

Morecambe Offshore Windfarm is a 480 MW offshore wind farm with 35 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 December 2025, not yet built; the record was last updated on 25 March 2026. REPD gives no grid reference for it. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010121).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

480 MWoffshore wind farm
approved, not builtstatus in REPD
25 March 2026record last updated
location not in REPDREPD location

Consent timeline

DateStage
31 May 2024Application submitted
1 December 2025Development consent granted (Secretary of State)
1 December 2032Permission due to expire (unless work starts)

Project details

Technology
offshore wind farm
Capacity
480 MW
Turbines
35
Turbine capacity
13.7 MW
Turbine height
310 m
Status (REPD)
approved, not built
Record last updated
25 March 2026
Operator or applicant
Cobra Instalaciones y Servicios S.A / Flotation Energy
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010121
Time to decision
78 weeks
Name in REPD
Morecombe Offshore Windfarm
REPD reference
10922

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010121). All Energy Secretary decisions on solar and wind farms.

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions.