North Nesting Wind, Shetland (250 MW)

North Nesting Wind, Shetland is a 250 MW wind farm project in Shetland Islands, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 20 September 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

250 MWwind farm
abandonedstatus in REPD
20 September 2018record last updated
Shetland Islandscouncil area

Planning timeline

REPD records no planning dates for this project.

Project details

Technology
wind farm
Capacity
250 MW
Status (REPD)
abandoned
Record last updated
20 September 2018
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Address (REPD)
Old Schoolhouse, Brettabister, Shetland
Council area (by location)
Shetland Islands
REPD reference
2978

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Viking Wind Farmwind farm443operational3.0
Muckla Moorwind farm249application withdrawn8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (60.3175, -1.1773).