Energy Projects Near You

Renewable energy projects in Shetland Islands

20 solar, wind or battery projects of 150 kW or more are located in Shetland Islands (REPD, July 2026 extract): 3 pending, 7 approved but not running, 7 operational and 0 refused. The council refused 0 of 11 decided applications (0%; UK 19%), with a median 25 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects in the council area
3awaiting a decision
7approved, not running
0%of decisions refused

How Shetland Islands decides

ApplicationsShetland IslandsUK
Decided applications (solar, wind, battery)1110,236
Refused0 (0%)19%
Solar refused0 of 112%
Onshore wind refused0 of 945%
Battery storage refused0 of 116%
Median time from submission to decision25.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Shetland Islands

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Viking Wind Farmwind farmwind farm443operationalupdated Jan 2022Nov 2018granted May 2019Jan 2022
North Nesting Wind, Shetlandwind farmwind farm250abandonedupdated Sep 2018——Sep 2018
Muckla Moorwind farmwind farm249application withdrawnupdated Jun 2008——Jun 2008
Energy Isles Wind Farmwind farmwind farm126approved, not builtupdated Oct 2023Apr 2019granted Oct 2023Oct 2023
Shetland Battery Energy Storage Systembattery storagebattery storage70under constructionupdated Jul 2026Jul 2023granted Feb 2024Jul 2026
Beaw Field Wind Farmwind farmwind farm59.5approved, not built may be out of dateupdated Mar 2023Apr 2016granted Nov 2017Mar 2023
Mossy Hillwind farmwind farm46.8approved, not built may be out of dateupdated Mar 2022Jun 2018granted May 2019Mar 2022
Luggies Knowe, Hill Of Gremista Wind Turbines & Battery Storagebattery storagebattery storage14.9approved, not builtupdated May 2025Jan 2024granted Apr 2025May 2025
Hill Of Wetherstawind farmwind farm10application submittedupdated Mar 2026Mar 2026—Mar 2026
Sullom Voe Terminal, Callbacknesswind farmwind farm9.6application submittedupdated Jan 2026Dec 2025—Jan 2026
Luggies Knowe, Hill Of Gremista Wind Turbines & Battery Storagewind turbinewind turbine5approved, not builtupdated May 2025Jan 2024granted Apr 2025May 2025
North Yell Wind Farm (Garth Community Wind Farm)wind farmwind farm4.5operationalupdated Sep 2018May 2009granted Apr 2011Sep 2018
Burradale Hillwind farmwind farm3.7operationalupdated Oct 2009Oct 1993granted Feb 1994Oct 2009
Gremista Wind Farmwind turbinewind turbine3operationalupdated Mar 2016Aug 2011granted Feb 2012Mar 2016
Culterfield, Cunningsburgh Windwind farmwind farm2.7application submitted may be out of dateupdated Mar 2022May 2021—Mar 2022
North Hoo Fieldswind turbinewind turbine2.3approved, not builtupdated Jan 2025Nov 2023granted Jul 2024Jan 2025
Northern Isles New Energy Solution (NINES) 1battery storagebattery storage1operationalupdated Jul 2017——Jul 2017
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Foula Community Electricity Schemebattery storagebattery storage—operationalupdated Dec 2018Dec 2009—Dec 2018
Gunnista, Bressay Solar panelsrooftop solarrooftop solar—operationalupdated May 2021Feb 2021granted Jul 2021May 2021
Gremista Greener Grid Park Stabilisation Facilitybattery storagebattery storage—application withdrawnupdated Jul 2023Feb 2023—Jul 2023

Postcode districts in Shetland Islands

DistrictProjects within 10 kmPendingApprovedOperational
ZE110054
ZE23001
ZE30000

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Shetland Islands by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.