Shetland Battery Energy Storage System (70 MW)

Shetland Battery Energy Storage System is a 70 MW battery storage project in Shetland Islands, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 April 2026; the record was last updated on 13 July 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

70 MWbattery storage
under constructionstatus in REPD
13 July 2026record last updated
Shetland Islandscouncil area

Planning timeline

DateStage
28 July 2023Application submitted
21 February 2024Section 36 consent granted (Scottish Ministers)
1 April 2026Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
70 MW
Status (REPD)
under construction
Record last updated
13 July 2026
Operator or applicant
Zenobe Energy
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004881
Address (REPD)
Lower Blackhill Industrial Estate, Genista, Lerwick
Council area (by location)
Shetland Islands
Time to decision
30 weeks
REPD reference
12856

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Luggies Knowe, Hill Of Gremista Wind Turbines & Battery Storagewind turbine5approved, not built1.0
Luggies Knowe, Hill Of Gremista Wind Turbines & Battery Storagebattery storage14.9approved, not built2.1
Mossy Hillwind farm46.8approved, not built2.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (60.1692, -1.1689).