Mossy Hill (46.8 MW wind farm)

Mossy Hill is a 46.8 MW wind farm project in Shetland Islands, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 May 2019, not yet built; the record was last updated on 30 March 2022. REPD records the planning permission as expiring on 26 May 2022, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

46.8 MWwind farm
approved, not builtmay be out of datestatus in REPD
30 March 2022record last updated
Shetland Islandscouncil area

REPD records the planning permission as expiring on 26 May 2022, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
27 June 2018Application submitted
27 May 2019Planning permission granted
26 May 2022Permission expired

Project details

Technology
wind farm
Capacity
46.8 MW
Status (REPD)
approved, not built
Record last updated
30 March 2022
Operator or applicant
Peel Wind Farms (Peel Energy)
Planning authority
Shetland Islands
Planning application reference
2018/186/PPF
Turbines
12
Turbine height
145 m
Address (REPD)
West of A970, includes Tagdale Hill, Hill of Dale, Mossy Hill and Bersa Hill, approx 2.4km from outskirts of Lerwick and approx 4.2km from Lerwick Harbour
Council area (by location)
Shetland Islands
Time to decision
48 weeks
Contracts for Difference
AR4
REPD reference
6384

Who decides

ApplicationsShetland IslandsUK
Decided applications (solar, wind, battery)1110,236
Refused0 (0%)19%
Solar refused0 of 112%
Onshore wind refused0 of 945%
Battery storage refused0 of 116%
Median time from submission to decision25.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shetland Battery Energy Storage Systembattery storage70under construction2.5
Luggies Knowe, Hill Of Gremista Wind Turbines & Battery Storagewind turbine5approved, not built3.5
Luggies Knowe, Hill Of Gremista Wind Turbines & Battery Storagebattery storage14.9approved, not built3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (60.1601, -1.2109).