Energy Projects Near You

Solar, wind and battery projects near Lerwick (ZE1)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ZE1 (Shetland Islands): 5 approved but not yet running, 4 operational. The largest live scheme is Shetland Battery Energy Storage System (70 MW battery storage, under construction since 1 April 2026), 2.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
0awaiting a decision
5approved, not running
4operational

Projects within 10 km of ZE1

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Northern Isles New Energy Solution (NINES) 1battery storagebattery storage1operationalupdated Jul 2017——Jul 2017Shetland Islands1.8
North Hoo Fieldswind turbinewind turbine2.3approved, not builtupdated Jan 2025Nov 2023granted Jul 2024Jan 2025Shetland Islands1.8
Shetland Battery Energy Storage Systembattery storagebattery storage70under constructionupdated Jul 2026Jul 2023granted Feb 2024Jul 2026Shetland Islands2.0
Mossy Hillwind farmwind farm46.8approved, not built may be out of dateupdated Mar 2022Jun 2018granted May 2019Mar 2022Shetland Islands2.4
Luggies Knowe, Hill Of Gremista Wind Turbines & Battery Storagewind turbinewind turbine5approved, not builtupdated May 2025Jan 2024granted Apr 2025May 2025Shetland Islands2.9
Burradale Hillwind farmwind farm3.7operationalupdated Oct 2009Oct 1993granted Feb 1994Oct 2009Shetland Islands3.9
Luggies Knowe, Hill Of Gremista Wind Turbines & Battery Storagebattery storagebattery storage14.9approved, not builtupdated May 2025Jan 2024granted Apr 2025May 2025Shetland Islands4.1
Gremista Wind Farmwind turbinewind turbine3operationalupdated Mar 2016Aug 2011granted Feb 2012Mar 2016Shetland Islands4.6
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gremista Greener Grid Park Stabilisation Facilitybattery storagebattery storage—application withdrawnupdated Jul 2023Feb 2023—Jul 2023Shetland Islands1.7
Gunnista, Bressay Solar panelsrooftop solarrooftop solar—operationalupdated May 2021Feb 2021granted Jul 2021May 2021Shetland Islands3.3

Distance from the average position of the ZE1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar100100
Wind farm2011046.8
Wind turbine302107.3
Battery storage4021084.9

MW in pipeline: pending, approved and under-construction capacity.

How Shetland Islands decides solar, wind and battery applications

ApplicationsShetland IslandsUK
Decided applications (solar, wind, battery)1110,236
Refused0 (0%)19%
Solar refused0 of 112%
Onshore wind refused0 of 945%
Battery storage refused0 of 116%
Median time from submission to decision25.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Shetland Islands

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ZE1, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.