Energy Projects Near You

Solar, wind and battery projects near Finstown (KW17)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW17 (Orkney Islands): 2 approved but not yet running, 2 operational. The largest live scheme is Orkney’s Community Wind Farm Project - Qanterness (28.8 MW wind farm, approved on 21 December 2021, not yet built), 3.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
2approved, not running
2operational

Projects within 10 km of KW17

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Orkney’s Community Wind Farm Project - Qanternesswind farmwind farm28.8approved, not builtupdated Oct 2022Feb 2020granted Dec 2021Oct 2022Orkney Islands3.3
Enyas Hillwind farmwind farm6refusedupdated Dec 2010Jul 2004refused Jan 2005Dec 2010Orkney Islands3.7
Orkney Storage Park Projectbattery storagebattery storage2operationalupdated Oct 2018——Oct 2018Orkney Islands6.3
Work Farm, Work Roadwind farmwind farm1.8application withdrawnupdated Feb 2024May 2023—Feb 2024Orkney Islands6.5
Hammars Hill Wind Farm Extensionwind farmwind farm8.4permission expiredupdated Sep 2024Apr 2020granted Sep 2021Sep 2024Orkney Islands7.6
Hammar's Hillwind farmwind farm4.3operationalupdated Oct 2010Mar 2008granted Jan 2009Oct 2010Orkney Islands7.6
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Harbour Authority Building, St Olawind farmwind farm—approved, not builtupdated Mar 2025Oct 2024granted Feb 2025Mar 2025Orkney Islands8.4

Distance from the average position of the KW17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm6021128.8
Battery storage100100

MW in pipeline: pending, approved and under-construction capacity.

How Orkney Islands decides solar, wind and battery applications

ApplicationsOrkney IslandsUK
Decided applications (solar, wind, battery)2910,236
Refused5 (17%)19%
Onshore wind refused5 of 2945%
Median time from submission to decision26.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Orkney Islands

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.