Energy Projects Near You

Solar, wind and battery projects near Stromness (KW16)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW16 (Orkney Islands): 1 is waiting for a planning decision, 1 approved but not yet running. The largest live scheme is Akla (2.7 MW wind farm, approved on 17 December 2012, not yet built; REPD status may be out of date), 8.2 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is West of Orkney Wind Farm (2,000 MW, approved, not built), 38.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
1awaiting a decision
1approved, not running
0operational

Projects within 10 km of KW16

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gruf Hillwind farmwind farm7.5refusedupdated Jul 2009Oct 2002refused Mar 2003Jul 2009Orkney Islands6.3
Aklawind farmwind farm2.7approved, not built may be out of dateupdated Sep 2022Dec 2010granted Dec 2012Sep 2022Orkney Islands8.2
Wind Turbine at Ward Hillwind turbinewind turbine2application submittedupdated May 2025Apr 2025—May 2025Orkney Islands8.9

Distance from the average position of the KW16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm201012.7
Wind turbine110002

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
West of Orkney Wind Farm2,000approved, not builtupdated Jul 202538.2

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Orkney Islands decides solar, wind and battery applications

ApplicationsOrkney IslandsUK
Decided applications (solar, wind, battery)2910,236
Refused5 (17%)19%
Onshore wind refused5 of 2945%
Median time from submission to decision26.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Orkney Islands

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KW16, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.