Ossian offshore wind farm
Ossian is a 3,600 MW offshore wind farm with 265 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 June 2025, not yet built; the record was last updated on 1 July 2025. REPD gives no grid reference for it. As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.
3,600 MWoffshore wind farm
approved, not builtstatus in REPD
1 July 2025record last updated
location not in REPDREPD location
Consent timeline
| Date | Stage |
|---|---|
| 10 July 2024 | Application submitted |
| 10 June 2025 | Marine licence and Section 36 consent granted (Scottish Ministers) |
Project details
- Technology
- offshore wind farm
- Capacity
- 3,600 MW
- Turbines
- 265
- Turbine capacity
- 13.5 MW
- Turbine height
- 399 m
- Status (REPD)
- approved, not built
- Record last updated
- 1 July 2025
- Operator or applicant
- Scottish Power Renewables
- Consenting authority (REPD)
- Marine Scotland
- Application reference
- not recorded
- Time to decision
- 48 weeks
- REPD reference
- 13429
Who decides
As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.
All offshore wind farms in UK waters
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions.