Owenreagh Extension (5.1 MW wind farm)

Owenreagh Extension is a 5.1 MW wind farm project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2008; the record was last updated on 29 July 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.1 MWwind farm
operationalstatus in REPD
29 July 2010record last updated
Derry City and Strabanecouncil area

Planning timeline

DateStage
1 January 2004Application submitted
1 October 2005Planning permission granted
1 August 2008Operational

Project details

Technology
wind farm
Capacity
5.1 MW
Status (REPD)
operational
Record last updated
29 July 2010
Operator or applicant
EF Energy
Planning authority
Derry City and Strabane
Planning application reference
J/2004/1015/F
Turbines
6
Address (REPD)
Land near Craignagapple 10km South East of Strabane, County Tyrone
Council area (by location)
Derry City and Strabane
Time to decision
91 weeks
REPD reference
2927

Who decides

ApplicationsDerry City and StrabaneUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused0 of 212%
Onshore wind refused10 of 4345%
Battery storage refused0 of 416%
Median time from submission to decision103.3 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Owenreagh Wind Farmwind farm5operational0.5
Craignapapple Wind Farmwind farm13.8approved, not built1.3
Koram Hillwind farm13.8application withdrawn2.4
Ballylawwind farm6.9application withdrawn7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8066, -7.3341).