Richborough Energy Park (49.9 MW)

Richborough Energy Park is a 49.9 MW battery storage project in Dover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2023; the record was last updated on 11 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
operationalstatus in REPD
11 January 2024record last updated
Dovercouncil area

Planning timeline

DateStage
4 November 2020Application submitted
13 May 2021Planning permission granted
1 December 2023Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
11 January 2024
Operator or applicant
Richborough Energy Park Limited
Planning authority
Thanet
Planning application reference
F/TH/20/1467
Address (REPD)
Richborough Energy Park
Council area (by location)
Dover
Time to decision
27 weeks
REPD reference
8195

Who decides

ApplicationsThanetUK
Decided applications (solar, wind, battery)2710,236
Refused2 (7%)19%
Solar refused1 of 2012%
Battery storage refused1 of 716%
Median time from submission to decision10.7 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Richborough Energy Park - Phase 2battery storage50.1operational<0.1
Richborough Energy Park - Phase 3 (Sheaf)battery storage249under construction0.3
Ebbsfleet Solar Farmsolar farm5operational0.3
Harrington Franklin, Richborough Energy Parkbattery storage49.9under construction0.8
Ebbsfleet Lanebattery storage49.9approved, not built0.9
Wharf Road, Discovery Parkbattery storage10approved, not built2.5
Minster Abbey, Bedlam Court Lanesolar farm33under construction2.8
Thorne Farmsolar farm6.2operational3.0
Land near Manstonsolar8.1refused3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.312, 1.343).