Solar, wind and battery projects near Ramsgate (CT11)
34 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CT11 (Thanet): 1 is waiting for a planning decision, 22 approved but not yet running, 10 operational. The largest live scheme is Richborough Energy Park - Phase 3 (Sheaf) (249 MW battery storage, under construction since 1 October 2024), 5.3 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Thanet (300 MW, operational), 18.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CT11
Projects of 1 MW and more (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Manston Solar Farm extension (Westwood)solar farm | solar farm | 9.2 | operationalupdated Apr 2014 | May 2013 | granted Jul 2013 | Apr 2014 | Thanet | 3.2 |
| Land near Manstonsolar | solar | 8.1 | refusedupdated Nov 2014 | Jul 2014 | refused Oct 2014 | Nov 2014 | Thanet | 3.4 |
| Sacketts Hill Farmbattery storage | battery storage | 22 | approved, not builtupdated Aug 2025 | May 2024 | granted Aug 2025 | Aug 2025 | Thanet | 3.6 |
| Manston Solar Farmsolar farm | solar farm | 9.9 | operationalupdated Jan 2014 | Sep 2012 | granted Nov 2012 | Jan 2014 | Thanet | 3.6 |
| Thorne Farmsolar farm | solar farm | 6.2 | operationalupdated Nov 2014 | Jul 2013 | granted Jan 2014 | Nov 2014 | Thanet | 4.6 |
| Hengrove Farm, Shottendane Road Solar Farmsolar farm | solar farm | 30 | approved, not builtupdated Sep 2024 | Sep 2023 | granted Aug 2024 | Sep 2024 | Thanet | 4.8 |
| Waste Processing Plant, Manston Road North Solar Farmsolar farm | solar farm | 2.7 | approved, not builtupdated Aug 2025 | Apr 2025 | granted Jul 2025 | Aug 2025 | Thanet | 4.8 |
| Ebbsfleet Lanebattery storage | battery storage | 49.9 | approved, not builtupdated Mar 2026 | Jul 2025 | granted Jan 2026 | Mar 2026 | Thanet | 4.9 |
| Ebbsfleet Farm Solar Farmsolar farm | solar farm | 4.9 | operationalupdated Apr 2012 | Jan 2011 | granted Mar 2011 | Apr 2012 | Thanet | 5.2 |
| Richborough Energy Park - Phase 3 (Sheaf)battery storage | battery storage | 249 | under constructionupdated Nov 2024 | Apr 2022 | granted Sep 2022 | Nov 2024 | Dover | 5.3 |
| Richborough Energy Park, Ramsgate Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated Sep 2023 | Aug 2023 | granted Sep 2023 | Sep 2023 | Dover | 5.5 |
| Richborough Energy Park - Phase 2battery storage | battery storage | 50.1 | operationalupdated Jan 2024 | Mar 2021 | granted Dec 2021 | Jan 2024 | Dover | 5.6 |
| Richborough Energy Parkbattery storage | battery storage | 49.9 | operationalupdated Jan 2024 | Nov 2020 | granted May 2021 | Jan 2024 | Dover | 5.6 |
| Jutes Lane, Weatherlees Hillsolar farm | solar farm | 3.3 | approved, not builtupdated Nov 2024 | Apr 2024 | granted Nov 2024 | Nov 2024 | Thanet | 5.6 |
| Harrington Franklin, Richborough Energy Parkbattery storage | battery storage | 49.9 | under constructionupdated Jun 2025 | Jun 2022 | granted Dec 2022 | Jun 2025 | Dover | 5.6 |
| Ebbsfleet Solar Farmsolar farm | solar farm | 5 | operationalupdated Jan 2016 | Sep 2013 | granted Jan 2014 | Jan 2016 | Dover | 5.9 |
| Compass House, Columbus Avenuerooftop solar | rooftop solar | 2 | application submitted | May 2026 | — | — | Thanet | 6.6 |
| Minster Abbey, Bedlam Court Lanesolar farm | solar farm | 33 | under constructionupdated Sep 2021 | Sep 2021 | — | Sep 2021 | Thanet | 6.7 |
| Wharf Road, Discovery Parkbattery storage | battery storage | 10 | approved, not builtupdated Nov 2024 | Jan 2024 | granted Nov 2024 | Nov 2024 | Dover | 6.8 |
| Hanet Earth, Barrow Man Road Solar Panel Arrayrooftop solar | rooftop solar | 1 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | Thanet | 9.1 |
| Marshborough Farm solar parksolar farm | solar farm | 5 | operationalupdated Feb 2016 | Feb 2015 | granted May 2015 | Feb 2016 | Dover | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ramsgate Sports Centre, High Street Solar Panels & Battery Storagebattery storage | battery storage | 0.4 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Thanet | 0.1 |
| Ramsgate Sports Centre, High Street Solar Panels & Battery Storagerooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Thanet | 0.1 |
| The Corporation Of St Lawrence College, College Roadrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Thanet | 0.8 |
| Fuji Film Sericol, Patricia Wayrooftop solar | rooftop solar | 1 | approved, not built may be out of dateupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Thanet | 2.0 |
| Hornet Close, Pysons Road Industrial Estate Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Jul 2024 | granted Apr 2025 | May 2025 | Thanet | 2.3 |
| Laleham Gap School, Ozengell Place Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Apr 2025 | granted May 2025 | Jun 2025 | Thanet | 2.3 |
| East Kent College, Ramsgate Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2026 | Nov 2025 | granted Dec 2025 | Apr 2026 | Thanet | 2.5 |
| Continental Approachrooftop solar | rooftop solar | 0.2 | operationalupdated Nov 2021 | Jun 2021 | granted Nov 2021 | Nov 2021 | Thanet | 3.9 |
| Queen Elizabeth The Queen Mothers Hospitalsolar farm | solar farm | 0.4 | operationalupdated Jan 2021 | Jul 2019 | granted Nov 2019 | Jan 2021 | Thanet | 5.0 |
| Solar Farm at To The S/O River Stoursolar farm | solar farm | — | approved, not built may be out of dateupdated Aug 2024 | Jul 2021 | granted May 2022 | Aug 2024 | Dover | 5.3 |
| Hengrove Farm House, Shottendane Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Oct 2025 | Jul 2025 | granted Aug 2025 | Oct 2025 | Thanet | 5.3 |
| Birchington Vale Caravan Park, Shottendane Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Thanet | 6.6 |
| Watson Yard, Monktonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2023 | Jan 2023 | granted Feb 2023 | Feb 2023 | Thanet | 6.7 |
Distance from the average position of the CT11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 0 | 5 | 7 | 0 | 69 |
| Rooftop solar | 12 | 1 | 10 | 1 | 0 | 6.8 |
| Solar | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 9 | 0 | 7 | 2 | 0 | 381 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Thanet | 300 | operationalupdated May 2018 | 18.5 |
| Kentish Flats | 90 | operationalupdated Oct 2017 | 26.1 |
| Kentish Flats 2 | 49.5 | operationalupdated Jun 2016 | 26.4 |
| London Array Phase 1 | 630 | operationalupdated Nov 2018 | 32.3 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Thanet decides solar, wind and battery applications
| Applications | Thanet | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 27 | 10,236 |
| Refused | 2 (7%) | 19% |
| Solar refused | 1 of 20 | 12% |
| Battery storage refused | 1 of 7 | 16% |
| Median time from submission to decision | 10.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CT11, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.