Sacketts Hill Farm (22 MW battery storage)

Sacketts Hill Farm is a 22 MW battery storage project in Thanet, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 August 2025, not yet built; the record was last updated on 19 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWbattery storage
approved, not builtstatus in REPD
19 August 2025record last updated
Thanetcouncil area

Planning timeline

DateStage
30 May 2024Application submitted
29 August 2024Refused by the planning authority
6 August 2025Planning permission granted
6 August 2025Appeal allowed
6 August 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
22 MW
Status (REPD)
approved, not built
Record last updated
19 August 2025
Operator or applicant
Greenfield Limited
Planning authority
Thanet
Planning application reference
F/TH/24/0575
Appeal reference
APP/Z2260/W/25/3361310
Address (REPD)
Land North Of Sacketts Hill Farm Sacketts Hill
Council area (by location)
Thanet
Time to decision
62 weeks
Name in REPD
Sacketts Hill Farm - Battery Energy Storage System
REPD reference
16556

Who decides

ApplicationsThanetUK
Decided applications (solar, wind, battery)2710,236
Refused2 (7%)19%
Solar refused1 of 2012%
Battery storage refused1 of 716%
Median time from submission to decision10.7 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manston Solar Farm extension (Westwood)solar farm9.2operational2.6
Hengrove Farm, Shottendane Road Solar Farmsolar farm30approved, not built2.9
Manston Solar Farmsolar farm9.9operational3.0
Land near Manstonsolar8.1refused3.7
Thorne Farmsolar farm6.2operational5.0
Ebbsfleet Lanebattery storage49.9approved, not built6.6
Minster Abbey, Bedlam Court Lanesolar farm33under construction7.1
Richborough Energy Park - Phase 3 (Sheaf)battery storage249under construction7.3
Richborough Energy Parkbattery storage49.9operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.368, 1.402).