Energy Projects Near You

Hengrove Farm, Shottendane Road Solar Farm (30 MW)

Hengrove Farm, Shottendane Road Solar Farm is a 30 MW solar farm project in Thanet, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 August 2024, not yet built; the record was last updated on 13 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
13 September 2024record last updated
Thanetcouncil area

Planning timeline

DateStage
21 September 2023Application submitted
28 August 2024Planning permission granted
28 August 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
13 September 2024
Operator or applicant
Industria Solar Bedworth Limited
Planning authority
Thanet
Planning application reference
F/TH/23/1209
Site area
41.5 ha
Address (REPD)
E And W/O Hengrove Farm, Shottendane Road, Margate
Council area (by location)
Thanet
Time to decision
49 weeks
Name in REPD
Hengrove Farm, Shottendane Road - Solar Farm
REPD reference
15013

Who decides

ApplicationsThanetUK
Decided applications (solar, wind, battery)2710,236
Refused2 (7%)19%
Solar refused1 of 2012%
Battery storage refused1 of 716%
Median time from submission to decision10.7 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manston Solar Farmsolar farm9.9operational1.4
Manston Solar Farm extension (Westwood)solar farm9.2operational1.6
Land near Manstonsolar8.1refused2.2
Thorne Farmsolar farm6.2operational2.9
Sacketts Hill Farmbattery storage22approved, not built2.9
Minster Abbey, Bedlam Court Lanesolar farm33under construction4.6
Ebbsfleet Lanebattery storage49.9approved, not built5.0
Richborough Energy Park - Phase 3 (Sheaf)battery storage249under construction5.8
Richborough Energy Park - Phase 2battery storage50.1operational5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3634, 1.3603).