Marshborough Farm solar park (5 MW)

Marshborough Farm solar park is a 5 MW solar farm project in Dover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 November 2015; the record was last updated on 1 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 February 2016record last updated
Dovercouncil area

Planning timeline

DateStage
14 February 2015Application submitted
29 May 2015Planning permission granted
15 September 2015Construction started
15 November 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 February 2016
Operator or applicant
Vogt Solar
Planning authority
Dover
Planning application reference
15/00115
Address (REPD)
Land at Marshborough Farm, Marshborough, Sandwich
Council area (by location)
Dover
Time to decision
15 weeks
REPD reference
5117

Earlier applications for this site

ApplicationMWSubmittedOutcome
Marshborough Farm solar park 13/0033212.84 May 2013refused 13 August 2013

Who decides

ApplicationsDoverUK
Decided applications (solar, wind, battery)2710,236
Refused7 (26%)19%
Solar refused3 of 1912%
Onshore wind refused4 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wharf Road, Discovery Parkbattery storage10approved, not built3.3
Ebbsfleet Solar Farmsolar farm5operational4.3
Harrington Franklin, Richborough Energy Parkbattery storage49.9under construction4.3
Richborough Energy Parkbattery storage49.9operational4.6
Richborough Energy Park - Phase 2battery storage50.1operational4.6
Richborough Energy Park - Phase 3 (Sheaf)battery storage249under construction4.7
Ebbsfleet Lanebattery storage49.9approved, not built5.4
Home Farm (Knowlton solar)solar farm11.5operational5.6
Minster Abbey, Bedlam Court Lanesolar farm33under construction6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2774, 1.3072).