Energy Projects Near You

Solar, wind and battery projects near Deal (CT14)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CT14 (Dover): 2 are waiting for a planning decision, 6 approved but not yet running, 4 operational. The largest live scheme is Elvington Solar Farm (49.5 MW solar farm, application submitted on 21 June 2025, no decision recorded), 7.1 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Thanet (300 MW, operational), 29.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
2awaiting a decision
6approved, not running
4operational

Projects within 10 km of CT14

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Engine Shed Fieldsolar farmsolar farm11refused on appealupdated May 2016Dec 2013refused Sep 2015May 2016Dover3.9
Barville Farm Wind Turbinewind turbinewind turbine1.5refused on appealupdated Oct 2015Oct 2013refused Aug 2014Oct 2015Dover6.6
Thornton Lanewind turbinewind turbine1.5refused on appealupdated Oct 2015Nov 2013refused Jun 2014Oct 2015Dover7.0
Elvington Solar Farmsolar farmsolar farm49.5application submittedupdated Aug 2025Jun 2025—Aug 2025Dover7.1
Elvington Battery Energy Storagebattery storagebattery storage49.5application submittedupdated Aug 2025Jun 2025—Aug 2025Dover7.1
North Dover Wind Parkwind farmwind farm10refusedupdated Mar 2009Sep 2007refused Mar 2009Mar 2009Dover7.4
Guston Court Farmsolar farmsolar farm27refusedupdated Oct 2014Feb 2014refused Sep 2014Oct 2014Dover7.5
Tilmanstone Collierysolar farmsolar farm10operationalupdated Feb 2016Aug 2013granted Mar 2014Feb 2016Dover7.6
Chalk Pit Solar Farmsolar farmsolar farm24under constructionupdated Jun 2026May 2022granted Nov 2022Jun 2026Dover7.6
Wharf Road, Discovery Parkbattery storagebattery storage10approved, not builtupdated Nov 2024Jan 2024granted Nov 2024Nov 2024Dover8.5
Land At Guston Court Farmsolar farmsolar farm5operationalupdated Feb 2016Dec 2014granted Mar 2015Feb 2016Dover8.5
Home Farm (Knowlton solar)solar farmsolar farm11.5operationalupdated Apr 2014May 2013granted Oct 2013Apr 2014Dover8.6
Marshborough Farm solar parksolar farmsolar farm5operationalupdated Feb 2016Feb 2015granted May 2015Feb 2016Dover8.7
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
West Streetrooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Jan 2026Mar 2026Dover1.4
Old Lorry Farm Shopsolar farmsolar farm—under constructionupdated Feb 2021Nov 2020granted Jan 2021Feb 2021Dover2.7
Chalk Pit Solar Farmbattery storagebattery storage—under constructionupdated Jun 2026May 2022granted Nov 2022Jun 2026Dover7.6
Kedleston Road Solar Panelsrooftop solarrooftop solar0.5approved, not builtupdated Oct 2020Dec 2020granted Feb 2021Oct 2020Dover9.3

Distance from the average position of the CT14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm9124273.5
Rooftop solar202000.7
Wind farm100010
Wind turbine200020
Battery storage3120059.5

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Thanet300operationalupdated May 201829.3
Kentish Flats 249.5operationalupdated Jun 201633.5
Kentish Flats90operationalupdated Oct 201733.8

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Dover decides solar, wind and battery applications

ApplicationsDoverUK
Decided applications (solar, wind, battery)2710,236
Refused7 (26%)19%
Solar refused3 of 1912%
Onshore wind refused4 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

All projects in Dover

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.