Energy Projects Near You

Land At Guston Court Farm (5 MW solar farm)

Land At Guston Court Farm is a 5 MW solar farm project in Dover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 December 2015; the record was last updated on 16 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 February 2016record last updated
Dovercouncil area

Planning timeline

DateStage
16 December 2014Application submitted
19 March 2015Planning permission granted
12 November 2015Construction started
20 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 February 2016
Operator or applicant
Conergy West Sussex
Planning authority
Dover
Planning application reference
14/01133
Site area
9.9 ha
Address (REPD)
Land At Guston Court Farm, Han, Guston, East Langdon Road, Dover, Kent
Council area (by location)
Dover
Time to decision
13 weeks
REPD reference
4952

Who decides

ApplicationsDoverUK
Decided applications (solar, wind, battery)2710,236
Refused7 (26%)19%
Solar refused3 of 1912%
Onshore wind refused4 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chalk Pit Solar Farmsolar farm24under construction0.9
Guston Court Farmsolar farm27refused1.0
North Dover Wind Parkwind farm10refused1.8
The Engine Shed Fieldsolar farm11refused on appeal5.3
Tilmanstone Collierysolar farm10operational7.7
Elvington Solar Farmsolar farm49.5application submitted8.8
Elvington Battery Energy Storagebattery storage49.5application submitted8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1487, 1.3283).