Energy Projects Near You

Solar, wind and battery projects near Dover (CT16)

16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CT16 (Dover): 3 are waiting for a planning decision, 6 approved but not yet running, 2 operational. The largest live scheme is Elvington Solar Farm (49.5 MW solar farm, application submitted on 21 June 2025, no decision recorded), 8.9 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Kentish Flats 2 (49.5 MW, operational), 37.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16projects within 10 km
3awaiting a decision
6approved, not running
2operational

Projects within 10 km of CT16

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land At Guston Court Farmsolar farmsolar farm5operationalupdated Feb 2016Dec 2014granted Mar 2015Feb 2016Dover2.1
North Dover Wind Parkwind farmwind farm10refusedupdated Mar 2009Sep 2007refused Mar 2009Mar 2009Dover2.8
Chalk Pit Solar Farmsolar farmsolar farm24under constructionupdated Jun 2026May 2022granted Nov 2022Jun 2026Dover3.0
Guston Court Farmsolar farmsolar farm27refusedupdated Oct 2014Feb 2014refused Sep 2014Oct 2014Dover3.1
The Engine Shed Fieldsolar farmsolar farm11refused on appealupdated May 2016Dec 2013refused Sep 2015May 2016Dover6.5
Barville Farm Wind Turbinewind turbinewind turbine1.5refused on appealupdated Oct 2015Oct 2013refused Aug 2014Oct 2015Dover6.6
Tilmanstone Collierysolar farmsolar farm10operationalupdated Feb 2016Aug 2013granted Mar 2014Feb 2016Dover7.6
Elvington Solar Farmsolar farmsolar farm49.5application submittedupdated Aug 2025Jun 2025—Aug 2025Dover8.9
Elvington Battery Energy Storagebattery storagebattery storage49.5application submittedupdated Aug 2025Jun 2025—Aug 2025Dover8.9
Snowdown Collierysolar farmsolar farm5permission expiredupdated May 2019Aug 2015granted Jan 2016May 2019Dover9.6
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kedleston Road Solar Panelsrooftop solarrooftop solar0.5approved, not builtupdated Oct 2020Dec 2020granted Feb 2021Oct 2020Dover1.0
Priory Court, St Johns Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Dover2.0
Westmount Education Centresolar farmsolar farm0.3approved, not built may be out of dateupdated Feb 2022Nov 2020granted Feb 2022Feb 2022Dover2.1
Chalk Pit Solar Farmbattery storagebattery storage—under constructionupdated Jun 2026May 2022granted Nov 2022Jun 2026Dover3.0
Channel House, Channel View Roadrooftop solarrooftop solar—application submittedMay 2026——Dover3.0
Bowles Well Gardensrooftop solarrooftop solar0.8approved, not builtupdated Aug 2022Jul 2022granted Aug 2022Aug 2022Folkestone and Hythe9.4

Distance from the average position of the CT16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8122273.8
Rooftop solar413001.6
Wind farm100010
Wind turbine100010
Battery storage2110049.5

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Kentish Flats 249.5operationalupdated Jun 201637.4
Kentish Flats90operationalupdated Oct 201738.1
Thanet300operationalupdated May 201839.5

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Dover decides solar, wind and battery applications

ApplicationsDoverUK
Decided applications (solar, wind, battery)2710,236
Refused7 (26%)19%
Solar refused3 of 1912%
Onshore wind refused4 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

All projects in Dover

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CT16, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.