Chalk Pit Solar Farm (24 MW)

Chalk Pit Solar Farm is a 24 MW solar farm project in Dover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 5 December 2025; the record was last updated on 3 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWsolar farm
under constructionstatus in REPD
3 June 2026record last updated
Dovercouncil area

Planning timeline

DateStage
24 May 2022Application submitted
25 November 2022Planning permission granted
5 December 2025Construction started

Project details

Technology
solar farm
Capacity
24 MW
Status (REPD)
under construction
Record last updated
3 June 2026
Operator or applicant
Greentech Services
Planning authority
Dover
Planning application reference
22/00668
Site area
28.9 ha
Address (REPD)
N/O Guston & The Lane, Guston Court Farm, Dover
Council area (by location)
Dover
Time to decision
26 weeks
Contracts for Difference
AR5
REPD reference
7911

The scheme also includes battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsDoverUK
Decided applications (solar, wind, battery)2710,236
Refused7 (26%)19%
Solar refused3 of 1912%
Onshore wind refused4 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Guston Court Farmsolar farm27refused0.1
Land At Guston Court Farmsolar farm5operational0.9
North Dover Wind Parkwind farm10refused1.5
The Engine Shed Fieldsolar farm11refused on appeal4.5
Tilmanstone Collierysolar farm10operational7.4
Elvington Solar Farmsolar farm49.5application submitted8.4
Elvington Battery Energy Storagebattery storage49.5application submitted8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.155, 1.337).