Energy Projects Near You

North Dover Wind Park (10 MW)

North Dover Wind Park is a 10 MW wind farm project in Dover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 16 March 2009; the record was last updated on 27 March 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
refusedstatus in REPD
27 March 2009record last updated
Dovercouncil area

Planning timeline

DateStage
15 September 2007Application submitted
16 March 2009Refused by the planning authority

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
refused
Record last updated
27 March 2009
Operator or applicant
Ecotricity
Planning authority
Dover
Planning application reference
DOV/07/01148
Turbines
5
Address (REPD)
Archers Court Road, East Langdon Dover
Council area (by location)
Dover
Time to decision
78 weeks
REPD reference
3033

Who decides

ApplicationsDoverUK
Decided applications (solar, wind, battery)2710,236
Refused7 (26%)19%
Solar refused3 of 1912%
Onshore wind refused4 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chalk Pit Solar Farmsolar farm24under construction1.5
Guston Court Farmsolar farm27refused1.6
Land At Guston Court Farmsolar farm5operational1.8
The Engine Shed Fieldsolar farm11refused on appeal3.7
Tilmanstone Collierysolar farm10operational5.9
Elvington Solar Farmsolar farm49.5application submitted7.0
Elvington Battery Energy Storagebattery storage49.5application submitted7.0
Home Farm (Knowlton solar)solar farm11.5operational8.7
Snowdown Collierysolar farm5permission expired9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1644, 1.3206).