Energy Projects Near You

Guston Court Farm (27 MW solar farm)

Guston Court Farm is a 27 MW solar farm project in Dover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 September 2014; the record was last updated on 6 October 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWsolar farm
refusedstatus in REPD
6 October 2014record last updated
Dovercouncil area

Planning timeline

DateStage
19 February 2014Application submitted
26 September 2014Refused by the planning authority

Project details

Technology
solar farm
Capacity
27 MW
Status (REPD)
refused
Record last updated
6 October 2014
Operator or applicant
Guston A Solar Farm Ltd & Guston C Solar Farm Ltd
Planning authority
Dover
Planning application reference
14/00153
Address (REPD)
Land at Guston Court Farm, East Langdon Road, Guston, Dover, CT15 5EX
Council area (by location)
Dover
Time to decision
31 weeks
REPD reference
2156

Who decides

ApplicationsDoverUK
Decided applications (solar, wind, battery)2710,236
Refused7 (26%)19%
Solar refused3 of 1912%
Onshore wind refused4 of 445%
Battery storage refused0 of 416%
Median time from submission to decision19.3 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chalk Pit Solar Farmsolar farm24under construction0.1
Land At Guston Court Farmsolar farm5operational1.0
North Dover Wind Parkwind farm10refused1.6
The Engine Shed Fieldsolar farm11refused on appeal4.5
Tilmanstone Collierysolar farm10operational7.4
Elvington Solar Farmsolar farm49.5application submitted8.4
Elvington Battery Energy Storagebattery storage49.5application submitted8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1556, 1.3382).