Rigghill Wind Farm (42 MW)

Rigghill Wind Farm is a 42 MW wind farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 March 2021; the record was last updated on 7 May 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWwind farm
refusedstatus in REPD
7 May 2021record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
27 April 2020Application submitted
29 March 2021Refused by the planning authority

Project details

Technology
wind farm
Capacity
42 MW
Status (REPD)
refused
Record last updated
7 May 2021
Operator or applicant
Burcote Wind
Planning authority
North Ayrshire
Planning application reference
20/00248/PPM
Turbines
10
Turbine height
150 m
Address (REPD)
Site To East Of Fardens, Skelmorlie, Strathclyde
Council area (by location)
North Ayrshire
Time to decision
48 weeks
REPD reference
7511

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Leapmoor Forestwind farm30application withdrawn3.9
Waterhead Moorwind farm72.5application withdrawn4.5
Berfern Farmbattery storage5permission expired5.1
Flatterton Farm, Flatterton Roadbattery storage49.9approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8555, -4.8535).