Energy Projects Near You

Royal Oak (6.5 MW wind farm)

Royal Oak is a 6.5 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 14 September 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWwind farm
abandonedstatus in REPD
14 September 2016record last updated
County Durhamcouncil area

Planning timeline

DateStage
22 February 2005Application submitted
10 January 2014Planning permission granted
10 October 2019Permission expired

Project details

Technology
wind farm
Capacity
6.5 MW
Status (REPD)
abandoned
Record last updated
14 September 2016
Operator or applicant
EDF Energy Renewables
Planning authority
Darlington
Planning application reference
05/00183/FULE
Turbines
5
Address (REPD)
Royal Oak Farm, Heighington, Darlington
Council area (by location)
County Durham
Time to decision
463 weeks
REPD reference
4268

Who decides

ApplicationsDarlingtonUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1712%
Onshore wind refused1 of 345%
Battery storage refused0 of 116%
Median time from submission to decision12.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Field at School Aycliffe Lanesolar farm5operational5.2
Toronto Green Energy Park, Addison Road Solar Farmsolar farm27application submitted6.5
Addison Roadbattery storage22abandoned6.8
Bluestone Farm, Low Lands Solar Farmsolar farm50approved, not built7.5
Whinfield Solar Farmsolar farm33approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6152, -1.6771).