Energy Projects Near You

Sofia (Teesside B) offshore wind farm

Sofia (Teesside B) is a 1,400 MW offshore wind farm with 100 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 March 2022; the record was last updated on 13 September 2022. Its REPD grid reference is 198 km from the nearest postcode on land (YO15 1AR, East Riding of Yorkshire). As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010051).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,400 MWoffshore wind farm
under constructionstatus in REPD
13 September 2022record last updated
198 km from land (East Riding of Yorkshire)REPD location

Consent timeline

DateStage
28 March 2014Application submitted
5 August 2015Development consent granted (Secretary of State)
1 March 2022Construction started

Project details

Technology
offshore wind farm
Capacity
1,400 MW
Turbines
100
Turbine height
252 m
Status (REPD)
under construction
Record last updated
13 September 2022
Operator or applicant
RWE Renewables UK Limited
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010051
Nearest postcode on land
YO15 1AR (East Riding of Yorkshire), 197.7 km from the REPD grid reference
Time to decision
71 weeks
Contracts for Difference
AR3
REPD reference
6556

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010051). All Energy Secretary decisions on solar and wind farms.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Dogger Bank C (was Teesside A)1,200under construction<0.1

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (55.21, 2.33).

Sofia, formerly Teesside B, is one of the most remote offshore wind farms in the REPD: its REPD point lies 198 km in a straight line from the nearest postcode, YO15 1AR in the East Riding of Yorkshire. Only Dogger Bank A and B (212 km) and the Culzean pilot project sit further out. The applicant in the register is RWE Renewables UK Limited; the site holds 100 turbines, each 252 m tall, for 1,400 MW in total.

Status according to the old record

The application was submitted on 28 March 2014; after examination by the Planning Inspectorate (EN010051), consent for a nationally significant infrastructure project (DCO) was granted on 5 August 2015, taking 71 weeks. It holds a Contract for Difference from allocation round AR3, and since 1 March 2022 the register has listed it as under construction. But the record has not been updated since 13 September 2022, so “under construction” in the July 2026 extract may be out of date.

Teesside A is now Dogger Bank C

The former Teesside A is called Dogger Bank C: 1,200 MW, under construction, with a separate record at the same point. Dogger Bank A and B are a third, standalone project.