Energy Projects Near You

Strathy South (208 MW wind farm)

Strathy South is a 208 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2025; the record was last updated on 11 September 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

208 MWwind farm
under constructionstatus in REPD
11 September 2025record last updated
Scotlandcouncil area

Planning timeline

DateStage
1 February 2009Application submitted
3 September 2014Appeal lodged
27 April 2018Section 36 consent granted (Scottish Ministers)
27 April 2018Appeal allowed
1 June 2025Construction started

Project details

Technology
wind farm
Capacity
208 MW
Status (REPD)
under construction
Record last updated
11 September 2025
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Scottish Government (S36)
Planning application reference
EC00003113
Appeal reference
WIN-270-2
Turbines
35
Turbine height
200 m
Address (REPD)
South of Strathy, Sutherland
Council area (by location)
not known
Time to decision
482 weeks
Contracts for Difference
AR5
REPD reference
4418

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Strathy Woodwind farm62.4under construction4.7
Strathy Northwind farm67.7operational6.0
Cairnview, Bettyhillwind farm48approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.44, -4.0735).