Cairnview, Bettyhill (48 MW wind farm)

Cairnview, Bettyhill is a 48 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 February 2024, not yet built; the record was last updated on 12 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
approved, not builtstatus in REPD
12 March 2024record last updated
Highlandcouncil area

Planning timeline

DateStage
12 January 2023Application submitted
26 February 2024Planning permission granted
26 February 2029Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
approved, not built
Record last updated
12 March 2024
Operator or applicant
Bettyhill 2 Wind Limited
Planning authority
Highland
Planning application reference
23/00142/FUL
Turbines
10
Turbine height
150 m
Address (REPD)
Land 2375M SE Of Cairnview Bettyhill
Council area (by location)
Highland
Time to decision
59 weeks
REPD reference
8535

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Phase 1 Bettyhill Wind Farmwind farm5operational3.4
Armadale Wind Farmwind farm43.2application withdrawn5.9
Loch Toftingall, Halsary Wind Farmbattery storage49.9approved, not built7.8
Strathy Northwind farm67.7operational7.9
Strathy Woodwind farm62.4under construction9.2
Strathy Southwind farm208under construction9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5089, -4.1653).