Phase 1 Bettyhill Wind Farm (5 MW)

Phase 1 Bettyhill Wind Farm is a 5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 June 2013; the record was last updated on 21 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
operationalstatus in REPD
21 March 2014record last updated
Highlandcouncil area

Planning timeline

DateStage
9 November 2007Application submitted
31 August 2011Planning permission granted
4 June 2013Operational

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
21 March 2014
Operator or applicant
North British Windpower Ltd
Planning authority
Highland
Planning application reference
07/00448/FULSU
Turbines
2
Address (REPD)
Skelpick Estate, Thurso KW14 7TA
Council area (by location)
Highland
Time to decision
199 weeks
REPD reference
3380

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cairnview, Bettyhillwind farm48approved, not built3.4
Armadale Wind Farmwind farm43.2application withdrawn6.8
Loch Toftingall, Halsary Wind Farmbattery storage49.9approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5356, -4.1947).